John Holland Rail Revitalisation Program (RRP) Work Package 1 – Beckenham to Sherwood

Upgrade the PTA train line.

Client: John Holland

Location: Armadale Line Beckingham to Sherwood Station, WA

Duration: August 2024 – March 2025

Scope of Works:  

  • Removal of existing ballast and capping layer
  • Installation of new drainage
  • Installation of access tracks
  • Reinstatement of new capping layer and ballast
  • Detailed excavations

Services Provided: PTA RIW compliant Supervisor and Operators. WET hire of GPS-UTS Graders, Watercarts, GPS Excavators, GPS Loaders, GPS Posi Tracks, Rollers and Tippers

Categories